人造石墙、地面施工流程:
1、清洁基面
2、基面批刮人造石胶黏剂
3、石材背面批刮人造石胶黏剂
4、粘接石材
5、矫正板缝
6、填缝
7、清理、养护
人造石台面施工流程:
1、开料
2、修边
3、黏接
4、打磨
5、上蜡、抛光
6、安装
7、清洁
施工要点:
1、人造石墙、地面施工,基面上批刮胶黏剂的厚度应在3毫米以上,石材背面上的厚度为2~3毫米。
2、粘贴石材的时间应符合胶黏剂的产品使用说明,粘接完成后,需用木锤轻轻敲打至人造石与基面完全贴合。
3、墙、地面人造石材铺设完成后,需14天后方可进行收缝,让水分充分蒸发。
Artificial stone wall, ground construction process:
1. Clean the base surface
2. Base surface batch scraping artificial stone adhesive
3. Scrape artificial stone adhesive on the back of the stone
4. Bonding stone
5. Correct the seam of the plate
6. Caulking
7. Cleaning and maintenance
Artificial stone countertop construction process:
1. Cutting
2. Trimming
3. Bonding
4. Grinding
5. Waxing and polishing
6. Installation
7. Clean
Construction points:
1, artificial stone wall, ground construction, the thickness of the base surface of the scraping adhesive should be more than 3 mm, the thickness of the back of the stone is 2 ~ 3 mm.
2, the time of pasting the stone should be in line with the adhesive product instructions, after the bonding is completed, it is necessary to gently beat with a wooden hammer until the artificial stone is fully fitted to the base surface.
3. After the wall and ground artificial stone are laid, it takes 14 days before the seam can be closed and the water can be fully evaporated.